Size routine filter stock from consumption and lead time, then see why a rarely used critical module needs a separate decision based on the effect of downtime.
Consumption during replenishment lead time helps size a stock of regularly used items. Rare components with a high consequence of failure need a separate decision based on duty, alternatives and downtime.
Use a consistent time unit
Estimate normal demand, realistic procurement lead time, usable stock and the reserve agreed for uncertainty. Review whether past issue history reflects normal consumption or a one-time turnaround purchase.
Two filter elements each week
At two elements per week and a six-week lead time, expected lead-time demand is twelve. Adding a four-element reserve gives a planning level of sixteen. The same arithmetic is not sufficient to decide whether to hold a rarely replaced critical module.
Enquiry checklist
| Item | What to record |
|---|---|
| Demand | Normal issues per unit of time. |
| Supply | Lead time and credible variation. |
| Criticality | Downtime exposure and available alternatives. |
Check the quotation Add the selling unit to each line: piece, set or pack. Request both the number of packs and the resulting number of usable pieces so quotations can be compared on the same basis.
Review reserves when lead times or maintenance intervals change. Keep the original assumptions so the next stock review can explain the number.