Prepare a vertical multistage pump enquiry with flow, head, fluid properties, supply and installation constraints.
A motor rating is useful for identifying an existing installation. To review hydraulic suitability, the supplier also needs a duty point: the required flow and the head the pump must provide at that flow.
Put flow and head on one line
For example, a request might state 12 m³/h at 42 m head. These are illustrative values. Add the normal operating point and any specified minimum or maximum demand, keeping the units alongside each figure.
Describe the fluid and conditions
Identify the liquid, temperature range and any relevant concentration or solids data. Provide the available suction conditions from the plant design. Ask the selection engineer to confirm the assumptions used if data are incomplete.
| Check | What to record |
|---|---|
| Duty point | Flow and head at the same operating point |
| Fluid | Liquid, temperature and service conditions |
| Evidence | Offered model code and marked performance curve |
Check the quotation Ask for the drawing revision used to identify the spare, with the offered item number marked. Use the same numbered position when comparing a complete assembly with a repair kit.
Separate site constraints from hydraulic duty
Record supply voltage and frequency, connection details, materials required and available installation space. For an existing pump, include a readable nameplate and identify which pipework or connections need to be retained.
Ask for the proposed curve
Request the curve for the actual offered stage configuration and speed, with the duty point marked. Compare the offered materials, seal, motor and delivery scope against the enquiry before reviewing the price.