A 24 V, 5 A load needs 20 Wh at the output for ten minutes. Use the example to compare DC UPS runtime claims at the actual load and battery conditions.
A DC UPS request should say what must keep running and for how long. Supply voltage and battery ampere-hours alone cannot establish how long the protected equipment will remain available.
Separate essential loads
List continuous and peak demand, the required hold-up period and operating temperature. Identify any status signal needed by the control system. Compare candidate systems using the same load and temperature.
Ten minutes for a five-ampere load
At 24 V and 5 A the nominal load is 120 W. Ten minutes therefore represents 20 Wh of ideal delivered energy. Losses, discharge limits, temperature and ageing affect the battery capacity required in practice.
Enquiry checklist
| Item | What to record |
|---|---|
| Load | Continuous and peak current. |
| Time | Required duration at the stated load. |
| Status | Alarm contact or communications interface. |
Check the quotation State the load during normal operation and during the most demanding part of the duty cycle separately. Ask which of these conditions determines the offered rating.
At the 24 V output, 20 Wh corresponds to about 0.83 Ah delivered to the load. A battery operating at a different voltage cannot be sized by copying that Ah value. Ask for the offered runtime at the specified 120 W load.
Request the assembled system's runtime curve or rated run time under the agreed conditions. Treat the ideal energy calculation as a cross-check.
Sample enquiry to ISATIS
Please quote a DC UPS for the listed essential loads. State guaranteed or documented hold-up time, battery configuration and the conditions used.