A bypass chamber’s 1,200 mm connection spacing is not necessarily its probe length. Locate the mounting reference and check the clearance for later removal.
The centre-to-centre distance between process connections does not necessarily equal the ordered probe length. Mark the probe-length reference and available withdrawal space on the chamber drawing.
Identify the head, probe and chamber separately
The transmitter and probe may carry different codes. Record the chamber bore and shape, upper connection and bottom clearance. For a probe-only replacement, confirm compatibility with the retained head and the fluid conditions.
A 1,200 mm dimension with the wrong reference
A drawing may show 1,200 mm between branch centres while the probe mounts above the upper branch. Copying that number straight into the order can specify the wrong length. Request a dimensioned drawing of the proposed probe.
Enquiry checklist
| Item | What to record |
|---|---|
| Length datum | Start and end points of the ordered dimension. |
| Chamber | Bore, mounting connection and end clearance. |
| Service | Fluid and whether total level or an interface is required. |
Check the quotation Put the flange reference face and both measurement endpoints on one dimensioned drawing. Ask for the proposed active range to be marked on the same drawing.
Check both installed length and clearance to remove the probe later. A probe can fit the chamber while being impossible to withdraw with equipment overhead.
Sample enquiry to ISATIS
Please quote a chamber probe compatible with our existing head. Show the order length and datum on the proposal drawing and list the mounting accessories included.