Define the simulated input, expected indication and acceptance tolerance for a panel FAT. A midpoint example shows which part of the field loop the test covers.
A factory acceptance test can cover specified panel functions before delivery. Its value depends on an agreed test boundary, input conditions, expected results and a record of exceptions.
Write the expected result beside each test
Identify the signal source, display or output being checked, acceptance limits and who records the result. Mark simulated field signals explicitly. List functions that require the installed field equipment for a later test.
Checking the midpoint of a 0–100 scale
For a specified linear input scaled from 0 to 100, a simulated midpoint should produce the expected midpoint indication within the agreed tolerance. This checks the defined panel function under simulation, while the actual field sensor remains outside that test.
Enquiry checklist
| Item | What to record |
|---|---|
| Input | Real or simulated source and test value. |
| Result | Expected response and acceptance tolerance. |
| Record | Actual result, exception and sign-off. |
Check the quotation Specify the evidence you need at acceptance. Link each record to the equipment tag or serial and ask which results will appear in the delivered report.
Request the draft FAT procedure before testing. Agree how open items will be recorded and checked after correction.
Sample enquiry to ISATIS
Please include a FAT procedure for the listed panel functions. Mark simulated inputs, expected results, acceptance limits and the handling of open items.